John Smith


[PDF]John Smithhttps://www.brentwood.gov.uk/pdf/25052016133700u.pdfCachedservices. Date and Time. Description of works. Saturday 7 May 2016 23:00 hour...

5 downloads 441 Views 216KB Size

Contact & Communities Network Rail

Railway Neighbour

One Eversholt Street London NW1 2DN 3 May 2016

T 03457 11 41 41

Reference: LTN1 20+0344

Dear Neighbour, Crossrail Programme – Shenfield Station – Update Network Rail is undertaking essential improvement works in your area as part of the Crossrail Programme, linking Reading and Heathrow in the west to Shenfield and Abbey Wood in the east, via new tunnels under central London. At Shenfield, Network Rail is adding an additional platform (Platform 6) to accommodate the new longer, high capacity trains and will be installing new help points, customer information screens, public address systems and CCTV. The following information is a summary of planned works in your area over the coming weeks: Station works Date and Time

Description of works Work continues to re-profile the existing embankment behind May 2016 – May 2017 platform 5 to accommodate the new track, working back towards the southern end of platform 5 and Friars Avenue. Some sections of the embankment will need reinforcement Core working hours: with steel piles, we will recycle redundant sections of rail to Monday-Friday 08:00-18:00 form a base for rock filled gabion baskets. Saturday-Sunday 08:0013:00 Some weekend working Typically 23:30hrs Saturday to 05:00hrs Monday

Delivery of materials to site will be by rail where possible, or road via agreed lorry routes, outside of peak times. Normal lorry movements will be between 10am and 3pm, and traffic marshals will be used to ensure safe entry to site.

Trackwork We have started to remodel the existing track sidings at the east of Shenfield Station. The sidings are being remodelled to accommodate the new, longer trains which will come into service in 2017. Much of the work involves the use of engineering trains and rail mounted machinery including

Network Rail Infrastructure Limited Registered Office: Network Rail, 2nd Floor, One Eversholt Street, London, NW1 2DN Registered in England and Wales No. 2904587 www.networkrail.co.uk

excavators and specialised track equipment. Taking posession of the sidings, some work can be completed during daytime hours, Monday to Friday without affecting train services. Other works will have to be completed during the weekend including overnight activities to avoid disruption to train services. Date and Time Saturday 7 May 2016 23:00 hours To Monday 9 May 2016 05:00 hours Some mid-week working: Monday 9 May – Friday 13 May

Description of works Installation of 14 new overhead line structures adjacent to Abbots Close and Princes Way. Weekend works adjacent to Hunter Avenue – Excavation for new east siding number 1.

Midweek works adjacent to Hunter Avenue for construction of new sidings – excavation, ballasting and installation of new under track cable crossing adjacent to Hunters Avenue.

08:00-18:00 Sunday 15 May 2016 00:05 hours To Monday 16 May 2016 05:00 hours Some mid-week working: Monday 16 May – Friday 20 May 08:00-18:00

Weekend works adjacent to Hunter Avenue - Installation of ballast for new east siding number 1. Removal of redundant overhead line structures adjacent to Friars Avenue and Gordon Road. Excavation for new overhead line structures adjacent to Gordon Road and Silver Birches. Installation of piled foundations for new overhead line structures adjacent to Gordon Road, Friars Avenue and Silver Birches (weekend 08:00 – 20:00 only). Midweek works adjacent to Hunter Avenue for construction of new sidings – Excavation, ballasting and installation of new under track cable crossing adjacent to Hunters Avenue. Excavation for new overhead line structures adjacent to Gordon Road and Silver Birches.

Sunday 22 May 2016 00:05 hours To Monday 23 May 2016 05:00 hours Some mid-week working:

Weekend works adjacent to Hunter Avenue - Installation of ballast for new east siding number 1. Removal of redundant overhead line structures adjacent to Friars Avenue and Gordon Road. Excavation for new overhead line structures adjacent to Gordon Road and Silver Birches. Installation of piled foundations for new OLE structures adjacent to Gordon Road, Friars Avenue and Silver Birches (weekend 08:00 – 20:00 only).

Monday 23 May – Friday 27 May

Midweek works adjacent to Hunter Avenue – Installation of rails and sleepers for new siding number 1.

08:00-18:00

Excavation for new overhead line structures adjacent to Gordon Road and Silver Birches.

Weekend works adjacent to Hunter Avenue - Complete Saturday 28 May 2016 02:00 Installation of new Sidings number 1, Removal of track from hours existing middle sidings. Excavation of ballast from sidings To area. Tuesday 31 May 2016 04:00 hours

Installation of new under track cable crossing adjacent to

Date and Time

Description of works Alexander Lane and Long Ridings Avenue. Installation of new under track cable crossing adjacent to Friars Avenue.

Some mid-week working: Tuesday 31 May – Friday 3 June 08:00-18:00

Installation of 11 new overhead line structures and removal of redundant structures adjacent to Gordon Road, Friars Avenue and Silver Birches. Installation of piled foundations for new overhead line structures adjacent to Alexander Lane and Hunters Avenue (weekend and bank holiday Monday 08:00 – 20:00 only). Excavation for new overhead line structures adjacent to Gordon Road and Silver Birches.

Saturday 4 June 2016 02:00 hours

Weekend works adjacent to Hunter Avenue - Excavation and earth works for new east siding number 2 and new Southend Loop Line.

To Monday 6 June 2016 04:00 hours

Some mid-week working: Monday 6 June – Friday 10 June 08:00-18:00

Saturday 11 June 2016 02:00 hours

Installation of new overhead line structures adjacent to Abbots Close, Gordon Road, Silver Birches and Princes Way.

Midweek works adjacent to Hunter Avenue – Earthworks for new Southend loop line in the vicinity of Alexander Lane Bridge. Excavation for new overhead line structures adjacent to Gordon Road and Silver Birches. Weekend works adjacent to Hunter Avenue - Excavation and earth works for new east siding number 2 and new Southend Loop Line.

To Monday 13 June 2016 04:00 hours Some mid-week working: Monday 13 June – Friday 17 June 08:00-18:00 Saturday 18 June 2016 02:00 hours

Midweek works adjacent to Hunter Avenue – Earthworks for new south end loop line in the vicinity of Alexander Lane Bridge. Excavation for new overhead line structures adjacent to Gordon Road and Silver Birches. Weekend works adjacent to Hunter Avenue - Excavation and earth works for new east siding number 2 and new Southend Loop Line.

To Monday 20 June 2016 04:00 hours Some mid-week working: Monday 20 June – Friday 24 June 08:00-18:00

Midweek works adjacent to Hunter Avenue – Earthworks for new south end loop line in the vicinity of Alexander Lane Bridge. Excavation for new overhead line structures adjacent to Gordon Road and Silver Birches.

Hunter Avenue Retaining Wall As part of the installation of new sidings east of Shenfield station we will construct a retaining wall at the top of the railway embankment, indicated by the red highlighted area on the image below. The wall will be constructed of rock filled gabion baskets, secured to the top of existing embankment using approx. 200 steel piles, driven into the ground. Due to the proximity of the operational railway the piling will have to take place at weekends and at night. Whilst each of the piles used will not take as long to install as those used for the overhead line structures, we anticipate significant noise levels from the piling operations. Our site team are currently in the advanced stages of planning the work and estimate starting pile installation in late May to early June. We will write to residents living close to the site with further information on the construction plan when the start date is confirmed.

We apologise for any inconvenience these works may cause. Whilst we do anticipate some of these works to be noisy at times, mitigations are in place to keep noise levels to a minimum. Due to works taking place on operational railway, much of our work has to be carried out at night and weekends when trains are not running for safety reasons. The local authority has been, and will continue to be, consulted through the Control of Pollution Act 1974 (Section 61) process regarding the implementation of the works. If you have any additional questions or concerns, please telephone our 24-Hour National Helpline on 03457 11 41 41 and for more information about the Crossrail Programme please visit www.crossrail.co.uk. Yours faithfully Darren Green Community Relations Executive Crossrail East Programme